500KW Grid tied - Sharm El Sheikh



500KW Grid tied - Sharm El Sheikh

Enersyscom congratulates Eng. Ahmed Mousa "GFC Co." for his company's success in installing their latest project at Sharm El Sheikh 500KW with "Net Metering" system.

The project was implemented with KACO new energy Global 's Powador Inverter 20.0 TL3

Project details:

Spec. production 2143 KWH/KWp/Year

Annual production 771,651 KWh

CO2 emissions saved 459907Kg / year

Installer : GFC > Green Focus & Consultancy- Solar Energy in Egypt

Supplier : Energy Systems Components

Hope our cooperation be fulfilled with great success in the future